ISSUANCE OF THE SINGLE PERMIT*

favorite_border
Add favorite
Procedure
Online
Cetateni
Companii
National

The single agreement represents the document with technical and legal value, which certifies obtaining the necessary endorsements/agreements for the authorization of construction works, based on which the construction/demolition permit can be issued.

Only authorization documentation whose urbanism certificate was issued by the President of the Arad County Council will be accepted for analysis by the Committee and issuance of the single agreement.

Only authorization documentation in electronic format, signed with an electronic signature (by the applicant, designer, project verifier, etc.) will be accepted for analysis by the Committee and issuance of the single agreement.

Documentation requiring endorsement by an issuer who has not concluded a protocol with the Arad County Council, and therefore is not a member of the Committee for the single agreement, will not be accepted for analysis by the Committee. For such documentation, the normal procedure for endorsement and authorization according to Law no. 50/1991 regarding the authorization of construction works, republished, with subsequent amendments and completions, will apply.

The applicant can choose which of the endorsing members of the committee to submit documentation to, in order to obtain the necessary endorsements/agreements.

The deadline for issuing the single agreement is 30 days from the registration (in the registry of the Arad County Council) of the request for issuing the single agreement. This deadline can be exceeded in exceptional situations when, due to the complexity of the work or the necessity to complete the documentation. In this case, the applicant will be informed about the status of their case. The CJA registration number is generated upon receipt of proof of fee payment and is separate from the PISEG number generated when the request is initiated in eDirect. All other deadlines mentioned in this procedure are calculated in working days.

The single agreement is issued only for favorable endorsements/agreements. For unfavorable endorsements, the applicant will apply separately to the corresponding endorser.

Only after the single agreement is issued, the normal authorization procedure can continue by submitting at the headquarters of the Arad County Council the application for issuing the construction/demolition permit and the remaining endorsements/agreements that were not the object of the single agreement, as well as payment of the authorization fee.
*
Details
The single agreement represents the document with technical and legal value, which certifies obtaining the necessary endorsements/agreements for the authorization of construction works, based on which the construction/demolition permit can be issued.

Only authorization documentation whose urbanism certificate was issued by the President of the Arad County Council will be accepted for analysis by the Committee and issuance of the single agreement.

Only authorization documentation in electronic format, signed with an electronic signature (by the applicant, designer, project verifier, etc.) will be accepted for analysis by the Committee and issuance of the single agreement.

Documentation requiring endorsement by an issuer who has not concluded a protocol with the Arad County Council, and therefore is not a member of the Committee for the single agreement, will not be accepted for analysis by the Committee. For such documentation, the normal procedure for endorsement and authorization according to Law no. 50/1991 regarding the authorization of construction works, republished, with subsequent amendments and completions, will apply.

The applicant can choose which of the endorsing members of the committee to submit documentation to, in order to obtain the necessary endorsements/agreements.

The deadline for issuing the single agreement is 30 days from the registration (in the registry of the Arad County Council) of the request for issuing the single agreement. This deadline can be exceeded in exceptional situations when, due to the complexity of the work or the necessity to complete the documentation. In this case, the applicant will be informed about the status of their case. The CJA registration number is generated upon receipt of proof of fee payment and is separate from the PISEG number generated when the request is initiated in eDirect. All other deadlines mentioned in this procedure are calculated in working days.

The single agreement is issued only for favorable endorsements/agreements. For unfavorable endorsements, the applicant will apply separately to the corresponding endorser.

Only after the single agreement is issued, the normal authorization procedure can continue by submitting at the headquarters of the Arad County Council the application for issuing the construction/demolition permit and the remaining endorsements/agreements that were not the object of the single agreement, as well as payment of the authorization fee.
*
Entitled persons
Regulated professions
Required documents

Denumire

Descriere

Obligatoriu

Semnătură digitală

Tip document

Descarcă


-
Request for issuance of single agreement*
Descarcă
Formular tipizat
obligatoriu cu semnatură digitală disponibil și prin OOTS
Urbanism certificate*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Technical documentation for authorizing the execution of works*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Technical documentation for obtaining approvals/agreements*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Issued documents

Denumire

Tip document

Descarcă


-
Unique agreement*
obligatoriu cu semnatură digitală disponibil și prin OOTS
Fees

Title

Value

Currency


Fee
Deadlines
Resolution time:
30
Calendar days
Case filling duration:
2
Calendar days
Notification deadline:
5
Calendar days
Appeal routes
In the case of a dispute between the beneficiary and the competent authority, the provisions of common law apply. For more details, consult the CAU Organization and Operation Regulation: http://www.cjarad.ro/activitate/urbanism/20-19-comisia-pentru-acord-unic.html.
*
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated: 
22 April 2026
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Institution responsible with document: 
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Arad County Council*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Str. Corneliu Coposu Nr.22
Telefon:
Fax: 0357731280
Email: consiliul@cjarad.ro
Table of contents

Institutional structure

Directia Arhitect Sef

This site is managed by the Romanian Digitalisation Authority and is an official website of the Romanian Government
Public Institutions
Need assistance?
EU Institutions
Info
PNRR. Finanțat de Uniunea Europeană
UrmătoareaGenerațieUE
© 2024 roepas.ro